Metro Line 3 Power Distribution Solution – Cairo, Egypt
Project Name: Cairo Metro Line 3 – Phase 4 Power Supply System
Country: Egypt
Supplied Products:
-
66/11kV 40MVA Oil-Immersed Power Transformers (2 units)
-
KYN28-12 11kV Indoor Switchgear Panels (54 panels)
-
VS1-12 Indoor Vacuum Circuit Breakers (withdrawable type)
-
RMU (Ring Main Units) for underground distribution (22 sets)
-
11/0.4kV Prefabricated Containerized Substations (8 units)
-
GCS/MNS Low Voltage Switchgear Panels (72 panels)
-
Reactive Power Compensation Panels (18 units)
-
Traction Power Supply Cabinets (750V DC output for trains)
Client: Egyptian National Authority for Tunnels (NAT) – via EPC Contractor Arab Contractors & VINCI
Application: Medium-voltage and low-voltage distribution for metro traction substations, signaling, station loads, and auxiliary systems
Project Overview:
QZ Switchgear supplied a complete traction power and auxiliary distribution package for Cairo Metro Line 3 expansion. The project involved delivering high-reliability substations for train traction, underground stations, signaling equipment, passenger facilities, and depot areas.
Technical Highlights:
Traction Power Supply
-
66/11kV transformers feeding into traction substations
-
Dedicated 750V DC traction cabinets to power metro trains
-
Redundant feeder design to ensure no single-point failure
Medium Voltage Side
-
KYN28-12 switchgear with VS1 vacuum breakers for incomer, feeder, and bus coupler applications
-
RMUs deployed in underground tunnels for compact distribution
-
IEC 62271 compliant, with relay protection integrated into metro SCADA
Low Voltage Side
-
LV switchgear panels serving station lighting, escalators, HVAC, fire safety, ticketing, and depot facilities
-
Reactive compensation panels improved power factor and reduced energy costs
-
Prefabricated substations shortened civil construction time
Client Benefits:
-
High reliability: Redundant design ensures continuous traction power and passenger safety
-
Customized engineering: Compact RMUs solved underground space constraints
-
Efficient execution: Prefabricated substations reduced construction schedule by 4 months